All posts from

Process of Construction B.E Question Paper : jaduniv.edu.in

Name of the University : Jadavpur University
Department : Construction Engineering
Degree : B.Tech
Subject Name : Process of Construction
Year/Sem : II/II
Website : jaduniv.edu.in
Document Type : Model Question Paper

Download Model/Sample Question Paper :
2013 : https://www.pdfquestion.in/uploads/dspace.jdvu.ac.in/6452-2013Process%20of%20Construction.pdf
2011 : https://www.pdfquestion.in/uploads/dspace.jdvu.ac.in/6452-Process%20of%20Construction.pdf

Process of Construction Question Paper :

Bachelor Of Engg. Construction Examination, 2013 :
Year : 2nd Year 2nd Semester
Time : Three hours.
Full Marks : 100

Related : Jadavpur University Construction Plants & Equipments B.E Question Paper : www.pdfquestion.in/6451.html

Answer any five questions. :
1. What kind of problem may arise during well sinking process? Describe every problem with neat sketch also discuss about the solutions of every problems. 20
2. What are the different types of pile foundation. Which type of pile foundation is mostly used in Kolkata. Describe that particular type of pile foundation with neat sketch. 20

3. Describe the process of SLIP FORM Technique fo a chimney (R.C.) with a neat sketch. 20
4. Why “THURST BORING” process was adopted for laying of 64// concrete pipes between palta and Tala under B.T.Road. Explain the process with neat sketch. 20

5. (a) For excavation we use “sheet pile”. Draw a typical cross section of sheet pile. What are the process for driving of sheet pile.
(b) Describe the process of arc welding with neat sketch.

6. Describe the process of “Box Pushing” to construct a underpass of railway embankment. What is the purpose of using aluminium sheet at the top of R.C.box during pushing method. 20

Bachelor Of Construction Engg. Examination, 2011 :
(2nd Year, 2nd Semester)
Process Of Construction :
Time : Three hours
Full Marks : 100
Answer any five questions. ;
1. KMC is laying 64¢¢dia concrete pipe under very congested BT Road. What process of construction is adopted for laying 64¢¢ dia pipe under very congested road without hampering traffic activity on the road. Explain the process of pipe laying with neat sketch. 20

2. KMRCL is constructing Howrah maidan metro station, total excavation depth is around 30 meter below ground level, as such no side space is available in Howrah maidan area. Which process is adopted for excavation of 30 meter depth in very congested place. Explain the process with every steps and neat sketch. 20

3. Write short note on. 20
a) Sheet piling
b) Poker vibrator
c) Box pushing method
d) Piston type concrete pump.

4. For bridge construction most commonly three process been adopted 20
a) Erection by pushing
b) Erection by crane/shear legs
c) Erection by using gantry girders.
Explain every process with neat sketch.

5. Explain the process of “well sinking”. What kind of defects may happened in well sinking process and what are the rectification measures explain with neat sketch. 20
6. a) Draw a sketch of typical column shuttering showing different component.
b) What is butt and fillet weld.
c) Explain “DMC” method of pilling with sketch.

Processes Of Construction :
Structures classified by methods materials of construction Timber, Masonry, Steel Framed, R.C. Framed, Prefab, Prestressed, Mass Concrete, etc. Modern structures: Geodesic Dome, Shells, Tension structures. Masonry-Brick and stone Masonry. Bond. Foundation with Lime concrete. Scaffolding, shuttering, Centering Conventional and Modern. Concrete-methods of Pouring. Reinforcement-bending, binding and congestion problems. Structural steel work-Riveting. Welding, Bolting, Black bolts and High Tensile bolts. Welding-Transformer, Generator, Electrodes, Welders Qualification, accessories. Building Finished-Flooring, Plastering. Stone Facing, Slip form construction, Cantilever construction of bridges.

Materials Of Construction :
Different construction materials, their properties, acceptance criteria. Brick, stone, lime, cement, stone gravel and sand, Iron and Aluminium -their properties and uses. Iron-Carbon system-thermal and mechanical treatment of iron and its alloys. Timber-common Indian species, classification, Detection Treatment, Seasoning, Plastics, and composite materials. Water for construction. Asbestos, Glass, Tar and Bitumen products Adhesives, paints and Vernishes, Use of local materials in construction. Polymeric materials plastics, Epoxy Resin, polyurethene, Fiberglass, FRP. Non-Ferrous Metals. Copper, Zinc, Non-Ferrous Alloys use in construction.

Construction Management-I :
Construction as an industry, Basic concepts of management. Planning Organising, controlling & Motivating. Different schools of management. Introduction to behavorial science, communication skills, leadership Applied psychology, project Formulation technoeconomic study, multidisciplinary approach, budget allotment, Facets of construction Management-General M, personnel M, contract M, contract Labour M, Material M., organisational structure-work Flow and information flow. Two-party and three-party models. In-house and offloading.